UFGS 01 32 17.00 20 Cost-Loaded Network Analysis Schedules (NAS)
Spec. Division
01 - General Requirements
CCR
Comments
Updated to clarify cost
Submitted by klloyd@nibs.org on Thu, 05/29/2025 - 20:25
Updated to clarify cost loading and price and payment procedures.
Complete review and update.
Submitted by klloyd@nibs.org on Thu, 05/29/2025 - 20:25
Complete review and update. Added new Related Materials: "Contractor Baseline Schedule General Commissioning/HVAC Review Checklist"
In response to the following
Submitted by klloyd@nibs.org on Thu, 05/29/2025 - 20:25
In response to the following CCRs: CCR 8739, paragraph "Construction Activities" (1.10.2.5.6) has been updated to clarify federal holidays; CCR 8891, clarified schedule deliverables due from the contractor and added checklists for the KTR as attachments (found under Related Materials) ; CCR 8971, revised Note in Submittals Article regarding Design-Build Requirements; and CCR 8823, changes to submittal requirements for NAVFAC PAC to mitigate schedule impacts: updated paragraphs "Project Baseline Schedule" (1.2.2), Submittal Article SD-01, and "DESIGNATED PROJECT SCHEDULER" (1.9).
Updated section to include
Submitted by klloyd@nibs.org on Thu, 05/29/2025 - 20:25
Updated section to include the required Oracle Primavera P6 software settings to be utilized in preparation and maintenance of the construction schedule and the tabular reports required to be submitted with each monthly invoice.
Corrected notes and
Submitted by klloyd@nibs.org on Thu, 05/29/2025 - 20:25
Corrected notes and paragraphs, for DB and DBB, on Baseline NAS submittals and requirements.
Combined with Design-Build
Submitted by klloyd@nibs.org on Thu, 05/29/2025 - 20:25
Combined with Design-Build Section 01 32 17.05 20. Updated Activity Identification and Organization, Design Activities, and Time Impact Analysis. Added Commissioning Activities.
Revised the Time Impact
Submitted by klloyd@nibs.org on Thu, 05/29/2025 - 20:25
Revised the Time Impact Analysis (TIA) action for Concurrent Delays
Administrative changes to use
Submitted by klloyd@nibs.org on Thu, 05/29/2025 - 20:25
Administrative changes to use of "must." Modified Monthly Network Analysis and Contract Administration paragraphs.
Title changed from NETWORK
Submitted by klloyd@nibs.org on Thu, 05/29/2025 - 20:25
Title changed from NETWORK ANALYSIS SCHEDULES (NAS); thoroughly revised to Primavera P6, Updated WBS & Activity Codes and Settings.
Modified subparts 1.4 and 1.4
Submitted by klloyd@nibs.org on Thu, 05/29/2025 - 20:25
Modified subparts 1.4 and 1.4 to add Primavera P6
Revised first note in subpart
Submitted by klloyd@nibs.org on Thu, 05/29/2025 - 20:25
Revised first note in subpart 1.6.2.5
INTERIM UPDATE: Section
Submitted by klloyd@nibs.org on Thu, 05/29/2025 - 20:25
INTERIM RELEASE: Section revised
Major revision
Submitted by klloyd@nibs.org on Thu, 05/29/2025 - 20:25
Major revision
Deleted requirements for
Submitted by klloyd@nibs.org on Thu, 05/29/2025 - 20:25
Deleted requirements for WEBCM
Deleted [DESIGN BUILD] from
Submitted by klloyd@nibs.org on Thu, 05/29/2025 - 20:25
Deleted [DESIGN BUILD] from the title and Design-Build requirements from the section.