UFGS 01 32 16.00 20 Small Project Construction Progress Schedules
Spec. Division
01 - General Requirements
CCR
Comments
In response to the following
Submitted by klloyd@nibs.org on Thu, 05/29/2025 - 20:25
In response to the following CCRs: CCR 8738, clarified adverse weather requirements and schedule modifications required due to non-work days in paragraph "Anticipated Weather Lost Work Days" (1.3.1.2); CCRs 8822 and 9013, changes to submittal requirements for NAVFAC PAC to mitigate schedule impacts: added Note under Submittal Article SD-01 and updated paragraph "PRE-CONSTRUCTION SCHEDULE REQUIREMENT" (1.2).
Updated Scheduling software
Submitted by klloyd@nibs.org on Thu, 05/29/2025 - 20:25
Updated Scheduling software settings and requirements and tailoring. Added Design-Build Requirements.
Revised the Time Impact
Submitted by klloyd@nibs.org on Thu, 05/29/2025 - 20:25
Revised the Time Impact Analysis (TIA) action for Concurrent Delays.
Administrative changes to use
Submitted by klloyd@nibs.org on Thu, 05/29/2025 - 20:25
Administrative changes to use of "must." Modified Monthly Network Analysis and Contract Administration paragraphs.
Title changed from
Submitted by klloyd@nibs.org on Thu, 05/29/2025 - 20:25
Title changed from CONSTRUCTION PROGRESS DOCUMENTATION; thoroughly revised Schedule Format, Schedule Monthly Updates, and Contract Modification.
Major revision
Submitted by klloyd@nibs.org on Thu, 05/29/2025 - 20:25
Major revision