UFGS 01 20 00 Price and Payment Procedures
Spec. Division
01 - General Requirements
CCR
Comments
Updated to clarify cost
Submitted by klloyd@nibs.org on Thu, 05/29/2025 - 20:25
Updated to clarify cost loading and price and payment procedures.
In response to CCR 12177,
Submitted by klloyd@nibs.org on Thu, 05/29/2025 - 20:25
In response to CCR 12177, replaced "lump sum" with "Job" in second Note for Army projects, removed "lump sum" from DREDGING paragraph (1.11).
In response to CCR 9972,
Submitted by klloyd@nibs.org on Thu, 05/29/2025 - 20:25
In response to CCR 9972, included timeline requirements for both Schedule of Prices and Earned Value Report and corrected typo in Note in Data Required paragraph.
In response to CCR 9618,
Submitted by klloyd@nibs.org on Thu, 05/29/2025 - 20:25
In response to CCR 9618, reference to FAR 32.503-6 has been replaced with "FAR 32.103 Progress payments under construction contracts" in paragraph (1.7.1) "Obligation of Government Payments" .
New Unified Section;
Submitted by klloyd@nibs.org on Thu, 05/29/2025 - 20:25
New Unified Section; Superseding UFGS 01 20 00.00 20 and UFGS 01 22 00.00 10 PRICE AND PAYMENT PROCEDURES