The diagram below represents the NAVFAC Six-Part format. This is the basic format for all NAVFAC Request for Proposals (RFP) and provides a logical separation of the information needed to describe the requirements of a project. Care must be taken to divide the information into the appropriate location among the Six-Part Format. The following is a description of the information that applies to each RFP Part (click on a folder below to jump to additional information about that particular part):
RFP Part 1 – Proposal Forms and Documents
Part 1 includes the Proposal Forms and other submittal documents which are prepared by the NAVFAC Contracting Officer using the Standard Procurement System (SPS), sometimes called PDD. These documents include the legal clauses of the contract and inform the contractor on how to do business with NAVFAC.
PART 1
Proposal Forms & Documents
Part 1 of the RFP Package is prepared by the Contract Specialist using PDD (Standard Procurement System). Samples in this site are for informational purposes only.
00001: Title Page |
00010: Table of Contents |
00100: Solicitation Form 1442 |
00101: Price Schedule |
00201: Instructions to Proposers |
00210: Evaluation Factors to Award |
00600: Representations and Certifications |
00710: Contract Clauses FAR 52.202-52.252 (full text) |
00720: Contract Clauses FAR 52.202-52.252 (by reference) |
00740: Contract Clauses for Foreign Projects |
00830: Davis-Bacon Wage Rates |
RFP Part 2 – General Requirements
Part 2 includes the traditional "Division 01" documents that address the administrative, safety, design processes, construction processes, and project closeout instructions for the project. These documents inform the contractor on how to do business with the local Base where the project is located and the NAVFAC Component creating the project.
PART 2
General Requirements
Part 2 of the RFP Package is prepared by the Specifications Engineer using standard UFGS and special design-build UFGS using SpecsIntact.
01 14 00 Work Restrictions |
01 20 00 Price and Payment Procedures |
01 30 00 Administrative Requirements |
01 31 19.05 20 Concept Design Workshop (CDW) |
01 31 23.13 20 Electronic Construction and Facility Support Contract Management System (eCMS) |
01 32 17.00 20 Cost-Loaded Network Analysis Schedules (NAS) |
01 33 00.05 20 Construction Submittal Procedures |
01 33 10.05 20 Design Submittal Procedures |
01 33 29 Sustainability Requirements and Reporting |
01 35 13 Special Project Procedures |
01 35 26 Governmental Safety Requirements |
01 45 00 Quality Control |
01 45 35 Special Inspections |
01 50 00 Temporary Construction Facilities and Controls |
01 57 19 Temporary Environmental Controls |
01 74 19 Construction Waste Management and Disposal |
01 78 00 Closeout Submittals |
01 78 23 Operation & Maintenance Data |
01 78 24.00 20 Facility Data Wordbook (FDW) |
01 91 00.15 Building Commissioning |
01 91 19 Building Enclosure Commissioning |
RFP Part 3 – Project Program
Part 3 provides the functional project requirements. This is the heart of the RFP and describes what the user of the facility needs and what NAVFAC wants to receive in the completed project. RFP Part 3 is divided into six chapters. RFP Part 3, Chapters 1-3 are in paragraph format describing design and site requirements; Chapters 4 and 5 are mostly tabular descriptions of the building and each room or space within the building; and Chapter 6 describes the engineering choices that are made by the RFP editor. Chapter 6 utilizes the Uniformat/ Workbreakdown Structure to allow systems descriptions of the facility and parallel the information structure and requirements of RFP Part 4.
PART 3
Project Program
Part 3 of the RFP Package is prepared by the Project Technical Team.
1. Project Description |
2. Project Objectives |
2.1. Mission Statement |
2.2. Facility Function |
2.3. Project Specific Priorities |
2.4. Appropriate Design |
2.5. Workflow Process |
2.6. Special Design Challenges |
2.7. Adaptability and Flexibility |
3. Site Analysis |
3.1. Existing Site Conditions |
3.2. Site Development Requirements |
4. Space Tabulation Form |
4.1. Space Tabulation |
4.2. Space Relationships |
4.3. Exterior Character |
5. Room Requirements |
6. Engineering Systems Requirements |
A10 Foundations |
A20 Basement Construction |
B10 Superstructure |
B20 Exterior Enclosure |
B30 Roofing |
C10 Interior Construction |
C20 Stairs |
C30 Interior Finishes |
D10 Conveying |
D20 Plumbing |
D30 HVAC |
D40 Fire Protection |
D50 Electrical |
E10 Equipment |
E20 Furnishings |
F10 Special Construction |
F20 Select BLDG Demolition |
G10 Site Preparations |
G20 Site Improvements |
G30 Site Mechanical Utilities |
G40 Site Electrical Utilities |
H10 Waterproof Structures |
H20 Graving Drydocks |
H30 Coastal Protection |
H40 Navigation Dredging and Reclamation |
H50 Waterfront Utilities |
H60 Waterfront Demolition |
H70 Waterfront ATFP |
RFP Part 4 – Performance Technical Specifications
Part 4 describes the performance and level of quality of the materials and systems of the facility. This RFP Part utilizes the Uniformat/ Workbreakdown Structure to allow systems performance requirements to be used. The RFP Editor must add materials and systems that are required for the facility but are not present in the DB template chosen but is not required to further edit this RFP Part. The Performance Technical Specifications used will depend on the Project requirements. Technical Team members edit the PTS guides for requirements within their design discipline.
PART 4
Performance Technical Specifications
Part 4 of the RFP Package is prepared by the Project Technical Team. The Performance Technical Specifications used will depend on the Project requirements. Technical Team members edit the PTS guides for requirements within their design discipline.
A10 Foundations |
A20 Basement Construction |
B10 Superstructure |
B20 Exterior Enclosure |
B30 Roofing |
C10 Interior Construction |
C20 Stairs |
C30 Interior Finishes |
D10 Conveying |
D20 Plumbing |
D30 HVAC |
D40 Fire Protection |
D50 Electrical |
E10 Equipment |
E20 Furnishings |
F10 Special Construction |
F20 Select BLDG Demolition |
G10 Site Preparations |
G20 Site Improvements |
G30 Site Mechanical Utilities |
G40 Site Electrical Utilities |
H10 Waterproof Structures |
H30 Coastal Protection |
H40 Navigation Dredging and Reclamation |
H50 Waterfront Utilities |
H60 Waterfront Demolition |
Z10 General Performance Technical Specification |
RFP Part 5 – Prescriptive Specifications
Part 5 is a place holder for UFGS Specifications in the situation that a facility has a prescriptive requirement. This Part is used judiciously in a situation that a facility has specific Navy or Marine Corps requirements that are not routinely used in the commercial market.
PART 5
Prescriptive Specifications
Part 5 of the RFP Package is prepared by the Project Technical Team. Prescriptive specifications should only be used when performance specifications will not meet the particular project requirements.
Prescriptive specifications are prepared from UFGS's edited for the requirements of the project. The number and type used will vary based on the project requirements.
RFP Part 6 – Attachments
Includes related information that supports the project, for example, surveys, studies, soils reports, environmental documentation, as-built drawings, existing conditions, forms, etc.
PART 6
Attachments
Part 6 of teh RFP Package is prepared by the Project Technical Team. The attachments used will depend on the project requirements but generally include the ones shown. Each Technical Team Member prepares attachments required for their discipline. Attachments may be in 8-1/2" x 11", 11" x 17" or D-size drawing format.
Permits Record of Decision (PROD) Form |
Geotechnical Report |
Site Survey |
. . . |