Status
Active
View/Download
Publish Date
Pages
39
Legacy Title Key
UFGS 33 52 43.13 Aviation Fuel Piping
Spec. Division
33 - Utilities
CCR
History: Below is a listing of the Revisions and Changes made to this UFGS.
KEY | PREPARING ACTIVITY (PA) | A Army | N Navy | F Air Force | S NASA [ARCHIVED] |
---|---|---|---|---|---|
ACTION | N New | R Revision | C Change | D Deletion |
Release | PA | Date | Action | Change # | Nature of Change or Revision |
---|---|---|---|---|---|
Feb-2021 | A | Aug-2018 | C | 1 |
Updated reference publication in paragraph 2.1.6 in response to CCR 8022. Deleted redundant submittal items in response to CCR 8765. Corrected misspelled words in response to CCR 9188. Updated paragraph Contractor Qualifications to align with UFGS 33 52 40 and UFGS 33 52 10 in response to CCR 8536. |
Aug-2018 | A | Aug-2018 | R |
Complete review and update. |
|
May-2014 | A | Feb-2010 | C | 2 |
Clarified washer material requirements as noted in CCR 2604 |
Feb-2010 | A | Feb-2010 | N |
New section |
Comments
Updated reference publication
Submitted by klloyd@nibs.org on Thu, 05/29/2025 - 20:34
Updated reference publication in paragraph 2.1.6 in response to CCR 8022. Deleted redundant submittal items in response to CCR 8765. Corrected misspelled words in response to CCR 9188. Updated paragraph Contractor Qualifications to align with UFGS 33 52 40 and UFGS 33 52 10 in response to CCR 8536.
Complete review and update.
Submitted by klloyd@nibs.org on Thu, 05/29/2025 - 20:34
Complete review and update.
Clarified washer material
Submitted by klloyd@nibs.org on Thu, 05/29/2025 - 20:34
Clarified washer material requirements as noted in CCR 2604
New section
Submitted by klloyd@nibs.org on Thu, 05/29/2025 - 20:34
New section