USACE ECB 2022-7 Interim Approach for Risk-Informed Designs for Dam and Levee Projects
Category
Guidance
Summary
This ECB provides interim guidance for incorporation of risk-informed design into on-going and future projects across all phases of work for dam and levee projects.